Dhablan
Dhablan
4 line Station
Esm Sudesh
Helper - Amit
Crank Handle zone - 12
Point and Crossing Inspection -
East Zone ( PTA side) - Point-13, Track - 21.
Inspection done by Incharge- 24 Jan 26
Compliance pending
West Zone ( NBA side) - Point 11,Track -20
Inspection done by Incharge on 25 Jan 26
Compliance pending.
TRD Inspection- 12 June 25.
Dhablan- PTA UP HASSDAC No 1 on Quad and Number 2 on OFC.
Self Inspection- 11 Feb 26
Points and Tracks and HASSDAC of PTA side.
Deff -
1.GTP insulation of Pt 65 A,64 A,64 B,TP 63, 62 B,61 A to be replaced.
2. Cleaning of ARA terminals inside all Point machines.
3. Cleaning of JB ( L-4) required.
Inspection of Nabha Side yard -
Point 71 a,70a,70b,71b,72,74 Lc 32 carried out.
Deff -
L bracket insulation of p 72 and p74 need replacement.
Fault of L2 SSDAC
If Dn HASSDAC failed due to train departure at PTA end,Ssdac of 03 Birthing fails due to train arrival, up SSDAC ( pta) side fails due to train.then SSDAC line 2 fails and clears without reset.
TSS is near the Location of SSDAC linec2 and line 3.
Solution-
1. Isolation transformer in quad.
2. Quad parameters
3. Earth value measurement
4. Slow to release facility on VPR.